Status as of 22 November 2026.
In short: Namma Metro runs about 103.6 km today, after the Pink Line’s elevated section opened on 14 November 2026. Two stretches are on track for 2027:
- the Pink Line underground from Dairy Circle to Nagawara (13.76 km);
- the Blue Line’s Outer Ring Road section from Central Silk Board to KR Puram (19.75 km).
The airport line is now due in March 2028. Phase 3 and Phase 3A will not open before 2031.
Bengaluru Metro Network Today (November 2026)
| Line | Route | Length | Status |
|---|---|---|---|
| Purple | Whitefield (Kadugodi) to Challaghatta | About 43.5 km | Operational (full line since October 2023) |
| Green | Madavara to Silk Institute | About 33.5 km | Operational (Madavara extension since November 2024) |
| Yellow | RV Road to Bommasandra | 19.15 km, 16 stations | Operational since 11 August 2025. Trains every 7 minutes at peak. |
| Pink (elevated) | Kalena Agrahara to Tavarekere (S.G. Palya) | 7.5 km, 6 stations | Operational since 14 November 2026. 33,409 riders on day one. |
Daily ridership averages about 10.5 lakh, with a record of 11.45 lakh in September 2026.
Metro Lines Expected to Open in 2027
1. Pink Line underground: Dairy Circle to Nagawara
- Length: 13.76 km, Bengaluru’s longest underground stretch.
- Stations (12): Dairy Circle, Lakkasandra, Langford Town, National Military School, MG Road, Shivajinagar, Cantonment, Pottery Town, Tannery Road, Venkateshpura, Kadugundanahalli, Nagawara.
- Interchanges: Purple Line at MG Road; Blue Line at Nagawara.
- Target: BMRCL has said between March and mid-2027. The main hold-up is Bengaluru’s first platform screen doors, which are still being installed and linked to signalling. No safety (CMRS) inspection has been reported yet.
- Areas that gain: Frazer Town, Cox Town, Richards Town, Kadugondanahalli and the NagawaraβThanisandra belt. This is the first rail link from these areas to MG Road and the south.
2. Blue Line Phase 2A: Central Silk Board to KR Puram (ORR)
- Length: 19.75 km elevated along the Outer Ring Road.
- Stations (13): Central Silk Board, HSR Layout, Agara, Ibbaluru, Bellandur, Kadubeesanahalli, Marathahalli, ISRO, Doddanekundi, DRDO Sports Complex, Saraswathi Nagar, KR Puram.
- Interchanges: Yellow Line at Silk Board; Purple Line at KR Puram.
- Status: trial runs began on 10 November 2026, covering about 6 km from KR Puram towards Doddanekundi.
- Target: May to mid-2027.
- Areas that gain: Bellandur, Kadubeesanahalli, Marathahalli and the ORR tech corridor. It is the most-awaited stretch for the area’s office workers.
Not Opening in 2027
| Project | Route | Latest target | Where it stands |
|---|---|---|---|
| Blue Line Phase 2B (airport line) | KR Puram β Hebbal β Kempegowda Airport, 38.44 km, 16 stations | March 2028 | Under construction. Earlier targets were September 2025, June 2026 and December 2026. |
| Phase 3 (Orange Line) | JP Nagar 4th Phase β Kempapura and Hosahalli β Kadabagere, 44.65 km | May 2031 | Civil tenders were cancelled in October 2026 after the double-decker design was dropped, and must be re-tendered. |
| Phase 3A (Red Line) | Sarjapur β Hebbal, 37.8 km | April 2033 | Revised plan sent to the Centre in April 2026. Union Cabinet approval is still awaited. |
| Tumakuru extension | Madavara β Tumakuru, 59.6 km | None | Detailed project report received in May 2026. No cabinet decision yet. |
How Reliable Are Metro Deadlines?
Not very, and this matters if you are paying a premium for “upcoming metro”. Some examples:
- The Yellow Line was promised for May 2025 and opened in August 2025.
- The Pink Line elevated section was first due in 2016. Recent targets were March 2026, then May, then 15 August, and it opened on 14 November 2026.
- Early in 2026 the state promised 41 km of new metro during the year. 7.5 km was delivered.
A useful rule: a stretch is close to opening once trial runs have started and the safety commissioner (CMRS) has inspected it. Today only the Blue Line’s ORR section has reached trial runs, and neither 2027 stretch has had a CMRS inspection.
What It Means for Property Buyers
- Price in the line that is running, not the one promised. Developers along the airport line already quote “metro proximity”, but that line is at least 15 months away.
- Walking distance matters more than the line. Homes within about 800 m of a station tend to see the rental benefit. Homes “5 km from a future station” mostly don’t.
- The ORR section changes daily commutes the most. If you work in Bellandur or Marathahalli, the stretch from Silk Board to KR Puram shortens the trip from the Yellow and Purple lines.
- North Bengaluru’s airport-line premium is a 2028 story. In Hebbal, Yelahanka and Bagalur, treat metro as a long-term benefit when comparing project prices. See our Hebbal 2026 analysis.
For how earlier lines affected prices and rents, read Bengaluru’s Metro Lines and Property Appreciation and North Bengaluru Metro Expansion: A Look Ahead to 2028.
FAQs
Q: Which Bengaluru metro lines open in 2027?
A: The Pink Line underground (Dairy Circle to Nagawara) and the Blue Line’s ORR section (Central Silk Board to KR Puram). Both are targeted for March to mid-2027.
Q: When will the airport metro open?
A: BMRCL’s latest target for the full Blue Line to Kempegowda Airport is March 2028.
Q: How long is the Bengaluru metro network now?
A: About 103.6 km, after the Pink Line elevated section opened on 14 November 2026.
Q: Is the Pink Line fully open?
A: Only the 7.5 km elevated part, Kalena Agrahara to Tavarekere, is open. The underground part to Nagawara is due in 2027.
Q: When will Sarjapur get metro?
A: The SarjapurβHebbal line (Phase 3A) is awaiting central approval and is targeted for April 2033.
Photo: Namma Metro viaduct by Aashim Tyagi, CC BY 2.0, via Wikimedia Commons.