B-RIDE, the agency building the Bengaluru suburban rail project, has awarded contracts to remove five level crossings on Corridor 4, the Kanaka line from Heelalige to Rajanukunte. The five gated crossings will be replaced by four road overbridges and one road underbridge, so road traffic no longer has to stop when a train passes. The line has 16 level crossings in all; the other 11 are not yet in a contract.
The work has gone to a joint venture of SV Constructions India Pvt Ltd and SLNS Earth Movers and Contractors, in two packages that also include service roads and drainage. B-RIDE managing director Lakshman Singh said physical construction is expected to start shortly.
The five crossings
| Package | Crossing | Location | Replaced by |
|---|---|---|---|
| Package 1 | LC-125 | Singena Agrahara | Two road overbridges and one road underbridge |
| LC-126 | Chintala Madiwala | ||
| LC-127 | Near Hoskuru station | ||
| Package 2 | LC-130 | Kodathi | Two road overbridges |
| LC-134 | Chinnappanahalli |
Key facts
| Item | Detail |
|---|---|
| Line | Corridor 4 (Kanaka), Heelalige to Rajanukunte, 46.88 km |
| Level crossings on the line | 16 |
| In this contract | 5, in two packages |
| Contractor | SV Constructions India Pvt Ltd and SLNS Earth Movers and Contractors (joint venture) |
| Also included | Service roads and drainage |
| Corridor 4 target | June 2029 |
Where Corridor 4 fits in the suburban rail plan
The suburban rail project has four corridors and 148 km of track. B-RIDE’s current targets are:
| Corridor | Route | Target |
|---|---|---|
| Corridor 2 (Mallige) | Baiyappanahalli – Chikkabanavara, 25.01 km | December 2028 |
| Corridor 4 (Kanaka) | Heelalige – Rajanukunte, 46.88 km | June 2029 |
| Corridor 1 | KSR Bengaluru – Devanahalli (airport), 49.9 km | March 2030 |
| Corridor 3 | Kengeri – Whitefield, 35.52 km | March 2030 |
The first prototype train is due in November 2027, from the order for 153 coaches for Corridors 2 and 4 placed with the Integral Coach Factory in May. Our earlier report covers the Corridor 2 tender.
What it means for people living along the line
Corridor 4 runs along the existing railway on the south-eastern and eastern edge of the city, the same line that crosses roads on the Sarjapur Road side and near Marathahalli. Kodathi and Chinnappanahalli both sit in areas with a lot of new housing, where residents already queue at closed gates whenever a train passes. Once the suburban service starts, trains will pass far more often, so the gates would close more often too; grade-separated crossings are what keeps road traffic moving after the line opens.
Two points for anyone buying near these crossings. A road overbridge changes the street in front of it: the approach ramps take space, and homes right beside one face a raised road and its traffic. And building it means a closed or diverted road for many months before the benefit arrives. The other 11 crossings on the line have no contract yet.
Which level crossings on Corridor 4 will be removed first?
Five: Singena Agrahara (LC-125), Chintala Madiwala (LC-126), near Hoskuru station (LC-127), Kodathi (LC-130) and Chinnappanahalli (LC-134).
What will replace the level crossings?
Four road overbridges and one road underbridge, with service roads and drainage around each.
Who is building them?
A joint venture of SV Constructions India Pvt Ltd and SLNS Earth Movers and Contractors, under two contract packages awarded by B-RIDE, the agency building the suburban rail project.
How many level crossings are there on Corridor 4?
Sixteen. This first phase covers five; the other 11 are not yet in a contract.
When will Corridor 4 of the Bengaluru suburban rail open?
B-RIDE’s target is June 2029. Corridor 2 (Baiyappanahalli–Chikkabanavara) is due first, in December 2028.
Sources
- Urban Acres: Bengaluru suburban rail to remove 5 level crossings (Nov 2026)
- Deccan Herald: Bengaluru suburban rail, first train in November 2027
Crossing names, numbers and packages are as stated by B-RIDE. Corridor targets are B-RIDE’s published dates.