The Karnataka cabinet has approved an extra ₹1,118.5 crore to finish the 134-km Anekal–Sarjapur–Varthur–Airport–Nelamangala ring road around Bengaluru. The project was sanctioned in 2017 at ₹2,290.5 crore. Its cost has now been revised to ₹3,409 crore, about 49% more, because of higher land costs, price escalation, delays and works added during construction.
The road is being built by the Karnataka Road Development Corporation Ltd (KRDCL). The approval came at the cabinet meeting on Thursday, 5 November 2026, and was announced by the office of Greater Bengaluru Development Minister Krishna Byre Gowda, who had inspected the road and asked the Public Works Department for the extra funds.
Key facts
| Item | Detail |
|---|---|
| Route | Anekal – Sarjapur – Varthur – Airport – Nelamangala, 134 km |
| Built by | Karnataka Road Development Corporation Ltd (KRDCL) |
| Sanctioned | 2017, at ₹2,290.5 crore |
| Revised cost | ₹3,409 crore |
| Extra funds approved | ₹1,118.5 crore, by the state cabinet on 5 November 2026 |
| Of which, land acquisition | ₹266.83 crore |
| Of which, price adjustment | ₹347.54 crore |
| New work added | 1.92-km elevated corridor at Varthur |
| Completion date | Not announced |
Where the extra ₹1,118.5 crore goes
Land acquisition takes ₹266.83 crore and price adjustment, the extra paid to contractors as material and labour costs rose, takes ₹347.54 crore. Those two items add up to ₹614.37 crore. The remaining ₹504.13 crore was not itemised in the announcement; it covers the other reasons the state gave for the revision, including delays and works added during construction, such as the Varthur elevated stretch.
The cabinet also recorded its concern at how long the road has taken. Nine years after sanction, officials were told to complete the pending works at the earliest, but no new deadline was set.
What the road connects
The state says the road will give Hoskote and Nelamangala a better link to Kempegowda International Airport, and a direct connection from Bidadi to Sarjapur via Varthur. For people living on the eastern side of the city, the main change is a route between Sarjapur Road, Varthur, Gunjur and Whitefield that does not depend on the Outer Ring Road or the inner city roads.
Varthur is the bottleneck the money is meant to fix. The 1.92-km elevated corridor is designed to carry through-traffic over the Varthur junction, where traffic from Gunjur, Whitefield and Sarjapur Road meets.
This road is easy to confuse with two others. It is not the BDA’s planned Peripheral Ring Road, and it is not the NHAI’s Satellite Town Ring Road (STRR), which runs much further out through Hoskote, Dobbaspet and Anekal.
What it means for buyers on the eastern side
Many of the projects we track on Sarjapur Road, in Gunjur and around Whitefield use Varthur as their daily route to work. A finished elevated corridor there would cut one of the worst delays on that commute. Further out, Hoskote and Nelamangala gain a faster run to the airport side once the full road is open.
Three points keep this in proportion. The money approves completion, it does not complete the road; the project is already nine years old. No completion date came with the approval. And the stretches still under construction, especially through Varthur, will mean diversions and dust for nearby residents before they bring any relief.
How much extra money has Karnataka approved for the ring road?
₹1,118.5 crore, approved by the state cabinet in early November 2026. That takes the project cost from ₹2,290.5 crore at its 2017 sanction to ₹3,409 crore.
Which areas does the 134-km ring road connect?
Anekal, Sarjapur, Varthur, the Kempegowda International Airport side and Nelamangala, with links towards Hoskote and Bidadi. It runs around the eastern and northern edge of Bengaluru.
Is this the same as the Peripheral Ring Road or the STRR?
No. This project is built by the Karnataka Road Development Corporation (KRDCL). The BDA’s Peripheral Ring Road and the NHAI’s Satellite Town Ring Road are separate projects.
What is the Varthur elevated corridor?
A 1.92-km elevated road at Varthur, added to the project to get through-traffic above the congested Varthur junction.
When will the ring road be completed?
No completion date was announced with the new funding. The cabinet noted the delays and told officials to finish the pending works as early as possible.
Sources
- Deccan Herald: Karnataka Cabinet approves additional Rs 1,118 crore for 134-km Anekal-Nelamangala ring road project
- Trade Brains: Bengaluru gets ₹1,118 crore push for peripheral road (7 Nov 2026)
Figures are as stated by the Greater Bengaluru Development Minister’s office. The 49% rise and the ₹504.13 crore balance are our own calculations from those figures.