The elevated viaduct of the Namma Metro Blue Line between Central Silk Board and KR Puram is now complete, and the work left on the 19.75 km Outer Ring Road stretch is at the stations. BMRCL’s physical progress table for the section shows every pile, pier and girder in place, with station entry and exit works at 85% and station roofing at 68%.
Greater Bengaluru Development Minister Krishna Byre Gowda inspected the trial runs on Tuesday, 24 November 2026. Trains are running from KR Puram towards Mahadevapura on the first four stations this month, and four more stations are due to join the trials in December. BMRCL is targeting a mid-2027 opening for the stretch.
Where the work stands
| Activity | Scope | Completed | Progress |
|---|---|---|---|
| Piles | 5,677 | 5,677 | 100% |
| Pile caps | 1,229 | 1,229 | 100% |
| Piers | 1,179 | 1,179 | 100% |
| U-girders cast | 1,171 | 1,171 | 100% |
| U-girders erected | 1,171 | 1,171 | 100% |
| Station entry and exit works | – | – | 85% |
| Station roofing | – | – | 68% |
The civil structure that carries the trains, from the foundations to the girders, is finished. What is left is the stations passengers will use: their entrances and exits, roofs and finishing. Earlier this month BMRCL also reported about 2 km of track installation and work at some stations still pending, with Silk Board, Iblur and Marathahalli among the stations behind schedule.
Trials, signalling and the opening date
The 33 kV power cables and third rail between the Baiyappanahalli depot and Marathahalli have been charged in stages since 30 October, which allowed the trials to move onto the mainline. The main pending system is signalling: the Railway Board gave in-principle approval in August for communications-based train control on the Blue and Pink lines, and the state government is targeting completion of the signalling installation by January 2027.
| Section | Target |
|---|---|
| Phase 2A: Central Silk Board to KR Puram, 19.75 km, 13 stations | Mid-2027 |
| Full 58.19 km line to Kempegowda International Airport | March 2028, moved from December 2027 |
The original deadline for the Silk Board–KR Puram stretch was December 2024. Our earlier report on the Blue Line trial runs covers the section-by-section opening dates and the stations on the airport line, and the Phase 2 station tracker follows each station.
The station design
BMRCL’s design for the ISRO station, one of the 13 on the stretch, wraps the elevated station in a perforated metal screen it calls “Urban Sieve”, with a pattern of triangular cut-outs under a blue curved roof and a panel showing a Bengaluru landmark at its centre.
What it means for the Outer Ring Road
The stretch runs along the Outer Ring Road through HSR Layout, Agara, Iblur, Bellandur, Kadubeesanahalli, Marathahalli and Doddanekundi to KR Puram, where it meets the Purple Line. That corridor holds most of Bengaluru’s large tech parks, and today its only public transport is the bus. For homes on Sarjapur Road and around Whitefield, a working Blue Line would give a rail link to the ORR offices and, through KR Puram, to the Purple Line.
The finished viaduct means the main construction risk on this stretch is behind it. The opening now depends on the stations, the signalling and the safety certification that follows the trials.
Is the Blue Line viaduct between Silk Board and KR Puram complete?
Yes. All 5,677 piles, 1,229 pile caps, 1,179 piers and 1,171 U-girders on the stretch have been built and erected, according to BMRCL’s progress table.
How far along are the Blue Line stations?
Station entry and exit works are 85% complete and station roofing 68%, as per BMRCL’s progress table.
When will the Silk Board–KR Puram metro open?
BMRCL is targeting mid-2027 for the 19.75 km Phase 2A stretch. Signalling installation is due to be completed by January 2027.
Where are Blue Line trial runs taking place?
Trials began from KR Puram towards Mahadevapura on the first four stations in November 2026. Four more stations are due to join the trials in December.
When will the Blue Line reach the airport?
The full 58.19 km line to Kempegowda International Airport is now targeted for March 2028, moved from December 2027.
How we compiled this
Progress figures are from BMRCL’s physical progress table for the Silk Board–KR Puram stretch. Another report this month put station entry and exit works at 88%; we show the figure in BMRCL’s table. The trial schedule and signalling date are as stated during the minister’s inspection on 24 November 2026; the power, track and approval details and the March 2028 airport target are as reported on 18 November 2026. The station description is from BMRCL’s design rendering.