Ejipura Flyover Set to Miss Another Deadline and May Not Be Fully Ready Even by January 2027

The Ejipura flyover is more than 80% complete but is unlikely to be fully ready even by January 2027, mainly because land is still needed near St. John’s Hospital.

Vikas H S By · News Desk ·
WhatsApp LinkedIn
Symmetrical view of the concrete underside of a road bridge and its piers
Photo: Dietmar Rabich, CC BY-SA 4.0, via Wikimedia Commons

The Ejipura flyover is set to miss yet another deadline. More than 80% of the work is complete, according to Greater Bengaluru Authority (GBA) officials, but the full flyover is unlikely to be ready even by January 2027. The current end-December 2026 target applies only to the right-side stretch.

What is done and what is pending

Work Progress
Main viaduct About 1.94 km of 2.09 km
Segments installed 582 of 629
Spans 49 of 54
Foundations 39 of 71
Pier caps 6 of 15
Reinforced earth panels Two-thirds cast, less than half installed
Footpaths 38%
Drains 39%
Crash barriers 4%
Median, asphalt surfacing and painting Not started

The ramp on the Madiwala side is complete.

Advertisement

The land problem

Some property belonging to St. John’s Hospital has been acquired, but more land is needed and talks are continuing. A GBA official said the authority is trying to open the flyover to traffic by the end of 2026, but that land acquisition may delay this.

Nine years since work began

  • May 2017: work starts under Simplex Infrastructure, with a November 2019 deadline.
  • 2019: the contractor stops work, citing unpaid dues, and the contract is later terminated.
  • November 2023: the remaining work is re-tendered.
  • 2024: BSCPL Infrastructure resumes work with a March 2026 target.
  • 2026: the deadline moves to October, which is also missed.

What this means if you live or plan to buy nearby

Expect construction and narrowed road space around the unfinished stretches into 2027. If commute time matters to your purchase in or around Koramangala, judge it on the roads as they are today, not on the flyover opening date.

When will the Ejipura flyover open?

There is no firm date for the full flyover. The end-December 2026 target covers only the right-side stretch, and the whole project is unlikely to be ready even by January 2027.

How much of the work is done?

More than 80%, according to Greater Bengaluru Authority officials.

What is holding it up?

Land acquisition, particularly near St. John’s Hospital, along with unfinished foundations, approach and finishing works.

When was it originally due?

November 2019.

How we compiled this

Progress figures and timelines are from a Greater Bengaluru Authority progress report and officials, as reported on 28 November 2026.