Bengaluru Suburban Rail: K-RIDE Invites Bids for the Last Two Kanaka Line Packages, Completing Tenders on Two Corridors

K-RIDE has invited bids for the last two civil works packages of Corridor 4, completing the tendering for the Mallige and Kanaka lines after L&T’s exit.

Vikas H S By · News Desk ·
WhatsApp LinkedIn
Close-up of steel railway tracks and points on stone ballast
Photo: Chris McKenna, CC BY-SA 4.0, via Wikimedia Commons

Karnataka Rail Infrastructure Development Company (K-RIDE) has invited bids for the last two civil works packages of Corridor 4, the Kanaka Line from Heelalige to Rajanukunte. With this, every civil package on Corridor 2 (Mallige Line) and Corridor 4 has been tendered. The two new packages are not yet awarded.

The two packages now out for bids

Package Stretch Main work
Package 3 Bellandur to Benniganahalli 3 km at grade and 4.3 km elevated, excluding stations
Package 4 Jakkur to Rajanukunte 6.6 km at grade and 5.2 km elevated, including a 1.7-km double-decker viaduct

On the double-decker section, Corridor 4 will run on the lower level and Corridor 1 above it.

Advertisement

Packages already awarded

Work Contractor Value
Corridor 4, Package 1 (Benniganahalli to Jakkur) RNS Infrastructure and Gayatri Projects JV ₹342 crore
Corridor 4, Package 2 (Heelalige to Bellandur) RNS Infrastructure ₹169 crore
Corridor 2, Package 1 Cemindia Projects ₹666 crore
Corridor 2, Package 2 (Chikkabanavara to Yeshwanthpur) PJB and CVCC JV ₹263.4 crore
Corridor 2, Package 3 (Yeshwanthpur to Benniganahalli) PJB Engineers ₹106.2 crore

Why the work was re-tendered

Larsen & Toubro held the original contracts for both corridors. Work stalled from March 2025 after a dispute over land handover, and K-RIDE decided in October 2025 to invite fresh tenders. Separately, contracts have been awarded to remove five level crossings on Corridor 4.

Where the timeline stands

  • Mallige Line (25 km, Benniganahalli to Chikkabanavara): targeted for December 2028.
  • Kanaka Line (46 km): targeted for June 2029.
  • Sampige Line (KSR Bengaluru to Devanahalli) and Parijaata Line (Kengeri to Whitefield): targeted for March 2030, with civil tenders yet to be invited.

The project’s overall deadline has moved to March 2030. Train delivery is also a risk: the coach factory building the 153 coaches is yet to appoint a design consultant.

What this means for home buyers

If you are buying near either corridor, treat these as target dates for a line that has already slipped. Do not pay a premium today on the assumption that trains will run on time.

What has K-RIDE tendered now?

Civil works Packages 3 and 4 of Corridor 4, the Kanaka Line between Heelalige and Rajanukunte.

Have these two packages been awarded?

Not yet. Bids have been invited.

When are the Mallige and Kanaka lines due?

The targets are December 2028 for the Mallige Line and June 2029 for the Kanaka Line.

What is the deadline for the whole project?

It has been extended to March 2030.

How we compiled this

Package, contract and schedule details are from K-RIDE’s tender and award information, as reported on 28 November 2026.