Karnataka Rail Infrastructure Development Company (K-RIDE) has invited bids for the last two civil works packages of Corridor 4, the Kanaka Line from Heelalige to Rajanukunte. With this, every civil package on Corridor 2 (Mallige Line) and Corridor 4 has been tendered. The two new packages are not yet awarded.
The two packages now out for bids
| Package | Stretch | Main work |
| Package 3 | Bellandur to Benniganahalli | 3 km at grade and 4.3 km elevated, excluding stations |
| Package 4 | Jakkur to Rajanukunte | 6.6 km at grade and 5.2 km elevated, including a 1.7-km double-decker viaduct |
On the double-decker section, Corridor 4 will run on the lower level and Corridor 1 above it.
Packages already awarded
| Work | Contractor | Value |
| Corridor 4, Package 1 (Benniganahalli to Jakkur) | RNS Infrastructure and Gayatri Projects JV | ₹342 crore |
| Corridor 4, Package 2 (Heelalige to Bellandur) | RNS Infrastructure | ₹169 crore |
| Corridor 2, Package 1 | Cemindia Projects | ₹666 crore |
| Corridor 2, Package 2 (Chikkabanavara to Yeshwanthpur) | PJB and CVCC JV | ₹263.4 crore |
| Corridor 2, Package 3 (Yeshwanthpur to Benniganahalli) | PJB Engineers | ₹106.2 crore |
Why the work was re-tendered
Larsen & Toubro held the original contracts for both corridors. Work stalled from March 2025 after a dispute over land handover, and K-RIDE decided in October 2025 to invite fresh tenders. Separately, contracts have been awarded to remove five level crossings on Corridor 4.
Where the timeline stands
- Mallige Line (25 km, Benniganahalli to Chikkabanavara): targeted for December 2028.
- Kanaka Line (46 km): targeted for June 2029.
- Sampige Line (KSR Bengaluru to Devanahalli) and Parijaata Line (Kengeri to Whitefield): targeted for March 2030, with civil tenders yet to be invited.
The project’s overall deadline has moved to March 2030. Train delivery is also a risk: the coach factory building the 153 coaches is yet to appoint a design consultant.
What this means for home buyers
If you are buying near either corridor, treat these as target dates for a line that has already slipped. Do not pay a premium today on the assumption that trains will run on time.
What has K-RIDE tendered now?
Civil works Packages 3 and 4 of Corridor 4, the Kanaka Line between Heelalige and Rajanukunte.
Have these two packages been awarded?
Not yet. Bids have been invited.
When are the Mallige and Kanaka lines due?
The targets are December 2028 for the Mallige Line and June 2029 for the Kanaka Line.
What is the deadline for the whole project?
It has been extended to March 2030.