Infrastructure Update: New Flyover Planned to Decongest Key Junction
The Bangalore Development Authority (BDA) has floated tenders for the construction of a four-lane flyover at Mekhri Circle, with an estimated project cost of around ₹420 crore. The proposed elevated corridor is aimed at addressing long-standing traffic congestion at one of North Bengaluru’s busiest junctions.
The flyover is planned as part of a broader decongestion strategy, with execution expected to be completed within 18 months from the start of construction.
Project Design and Connectivity Improvements
The proposed flyover will span approximately 1.6 km, beginning near the Hebbal flyover and extending toward Mekhri Circle (Rotary Junction). The project is expected to streamline traffic movement along this heavily used stretch, which connects key routes leading to the airport and central parts of the city.
The design includes multiple ramps and directional corridors to facilitate smoother traffic flow toward areas such as Yeshwanthpur, CV Raman Road, and Jayamahal Road. The project also integrates with existing and planned infrastructure, including a proposed short tunnel near Hebbal.
Project Snapshot
| Parameter | Details |
|---|---|
| Project | Mekhri Circle Flyover |
| Authority | Bangalore Development Authority (BDA) |
| Length | ~1.6 km |
| Cost | ₹420 crore (approx.) |
| Configuration | Four-lane flyover |
| Timeline | 18 months |
Strategic Importance of Mekhri Circle Corridor
Mekhri Circle is a critical junction connecting North Bengaluru, the airport corridor, and central city zones. The area experiences high traffic volumes due to its proximity to key institutional zones and arterial roads.
With growing vehicular movement toward Kempegowda International Airport and Yelahanka, infrastructure upgrades in this corridor have become increasingly necessary. The proposed flyover is expected to reduce travel delays and improve overall traffic efficiency.
Real Estate Impact: Boost for North Bengaluru Micro-Markets
The development of a major flyover in this corridor is expected to positively influence surrounding real estate markets. Improved connectivity typically enhances accessibility, which can drive both residential and commercial demand.
Areas such as Hebbal, Yelahanka, and surrounding North Bengaluru regions may benefit from reduced commute times and better road infrastructure. This, in turn, could support property value appreciation and increased interest from developers and investors.
Urban Mobility Outlook
The flyover project is part of a broader effort to address congestion across Bengaluru’s key junctions. As infrastructure projects continue to be implemented, the focus remains on improving connectivity between major corridors and supporting the city’s expanding urban footprint.