Quick answer
The Telangana Real Estate Regulatory Authority (TG RERA) has passed eight orders against Hyderabad developers. It fined Sanali IT Parks ₹25 lakh for marketing its unregistered Sanali The Edge project at Manchirevula, ordered five builders to refund a combined ₹1.19 crore with interest, and told two more to pay delay interest or hand over a flat. Builders that do not comply face further penalties under Section 63 of the RERA Act.
Published 18 November 2026 · Source: TG RERA orders reported on 17 and 18 November 2026
TG RERA has ruled against eight developers in a single round of orders covering unregistered projects, missing approvals, abandoned construction and delayed handovers in and around Hyderabad. The orders were reported on 17 November 2026.
What did TG RERA order?
| Developer | Order | Why |
|---|---|---|
| Sanali IT Parks | ₹25 lakh penalty within 30 days; stop marketing and selling until registered | Advertised Sanali The Edge at Manchirevula without TG RERA registration |
| Tripura Constructions | Refund ₹41.85 lakh with interest | Took payments but never got approvals or started construction |
| SVM Aditya Homes | Refund ₹27.16 lakh with interest | Collected money without HMDA approvals and did not build |
| Bhuvanteza Infra Projects | Refund ₹26 lakh with interest | Abandoned the project with no construction or possession |
| Sri Aditya Squares | Refund ₹17 lakh with interest | Buyer cancelled over delays; promised repayment never came |
| BVR Infra Developers | Refund ₹7 lakh with interest | Plot not registered or handed over; refund cheques not honoured |
| Vasavi Realtors | 10.85% a year on ₹49.50 lakh from 7 February 2025 until handover | Delayed possession of a flat |
| Arine Infraa | Hand over Flat 502 in Arine Emerald, Miyapur, immediately | Demanded ₹6.58 lakh the sale agreement and sale deed did not support |
Why was Sanali IT Parks fined?
Sanali IT Parks was marketing Sanali The Edge at Manchirevula, in the western suburbs near Narsingi, without registering it with TG RERA. That breaks Sections 3 and 4 of the RERA Act, 2016, which require a project to be registered before it is advertised or sold. Along with the ₹25 lakh penalty, payable within 30 days, the developer must immediately stop advertising, marketing, booking and selling units until the project is registered.
Which buyers get refunds?
Five builders must return a combined ₹1.19 crore (₹119.01 lakh) with interest. In most cases the money was taken for projects that never got going:
- Tripura Constructions, ₹41.85 lakh: collected substantial payments but did not obtain statutory approvals, begin construction or deliver the flat within a reasonable time.
- SVM Aditya Homes, ₹27.16 lakh: took money without the required HMDA approvals and neither started nor completed the project.
- Bhuvanteza Infra Projects, ₹26 lakh: abandoned the project, delivering neither construction nor possession. TG RERA had already fined the same developer ₹6.45 lakh for an unregistered project in 2025.
- Sri Aditya Squares, ₹17 lakh: the buyer cancelled because of construction delays, and the promoter promised to repay but did not.
- BVR Infra Developers, ₹7 lakh: failed to register the plot in the buyer’s name and hand over possession, and its repayment cheques were not honoured.
What about buyers who still want their homes?
Two orders keep the purchase alive. Vasavi Realtors must pay interest at 10.85% a year on the ₹49.50 lakh a buyer paid, counted from 7 February 2025 until the flat is handed over. Arine Infraa must immediately hand over Flat No. 502 in its Arine Emerald project at Miyapur. TG RERA rejected the developer’s demand for another ₹6.58 lakh in charges, finding nothing in the sale agreement or the registered sale deed to support it.
What this means if you are buying in Hyderabad
- A project that is advertised before it has a TG RERA number is breaking the law, whatever approvals the developer says are on the way. Sanali The Edge is the latest of several such cases, after Golden County in Keesara earlier this month.
- When a builder fails to start or finish a project, TG RERA can order the full amount back with interest, as five of these orders show.
- A builder cannot add charges at handover that are not in your sale agreement or sale deed. The Arine Emerald order turned on exactly that point.
- Choosing to stay in a delayed project does not mean losing out: the Vasavi order makes the builder pay interest every year until possession.